EMD Requirements Across States, Railways, CPWD and PSUs

TL;DR
Central goods procurement ordinarily uses 2–5% bid security under GFR Rule 170.
State tender laws differ. Tamil Nadu ordinarily limits EMD to 1%; other buyers may set department-specific terms.
Railway works and railway stores do not necessarily follow identical EMD provisions.
MSE and startup relief depends on the governing policy, procurement type, and tender clause.
Check the latest notice, corrigenda, and accepted security forms before submitting.
Two government tenders may ask for the same work and demand different deposits. That is not necessarily an error.
EMD rules depend on the buyer, procurement category, and law behind the tender. A contractor bidding for a state road project cannot simply apply the percentage used for a central goods purchase. The safer approach is to identify the governing rule first, then check the actual notice inviting tender (NIT).
Here is how to do that across major Indian buyers, without confusing bid security with the guarantee required after award.
How do central government EMD rules work under GFR?
EMD stands for Earnest Money Deposit. It is an amount that contractors or suppliers submit when bidding for a government tender to show their commitment to the offer. EMD acts as a financial safeguard for the buyer. It is generally refunded after the tender process, but may be forfeited if a bidder withdraws their offer or fails to meet certain conditions after winning the contract. |
For goods purchased by central ministries and departments, Rule 170 of the General Financial Rules, 2017 (Rule 170(i), PDF p. 42) ordinarily sets bid security at 2–5% of estimated value. On a ₹60 lakh purchase, that range is ₹1.2–3 lakh. The procuring ministry sets the amount in the bidding document; it is not calculated from your quoted price.
The same rule accepts insurance surety bonds, demand drafts, fixed deposit receipts, bankers’ cheques, bank guarantees, e-bank guarantees and approved online payment. Bid security normally stays valid for 45 days beyond bid validity. Rule 170(iii) also allows a bid-securing declaration in place of a deposit, with suspension consequences if the bidder breaks its undertaking.
Under Rule 170(ii), unsuccessful bidders ordinarily receive their security no later than 30 days after contract award. In two-stage bids, those eliminated at the first stage receive it within 30 days of that result. Eligible MSEs and DPIIT-recognised startups receive specified relief, but a medium enterprise cannot assume the same exemption. For the practical differences between cash, guarantees and bonds, see axiTrust’s guide to types of bid security.
Did you know? A bid-securing declaration does not freeze money, but it can still lead to suspension from future bids with the buyer if its conditions are breached. |
State-wise EMD rules: what changes across India

There is no single state EMD percentage for every Indian tender. Some states have detailed procurement laws; others rely on department manuals, government orders and standard bid documents. Compare the rule below with the current NIT before arranging funds.
1. Karnataka: EMD KTPP
The EMD KTPP question is not answered by importing the GFR 2–5% range.
Rule 12 of the Karnataka Transparency in Public Procurements Rules, 2000 requires EMD at the rates prescribed by departmental rules. It recognises demand drafts, bankers’ cheques, specified savings instruments, permitted electronic payment and, when approved, an irrevocable bank guarantee.
Confirm the relevant department schedule, payment mode, and exemption order in the tender. A works contractor and an equipment supplier may encounter different conditions.
2. Tamil Nadu: a clear statutory ceiling
Rule 14 of the Tamil Nadu Transparency in Tenders Rules, 2000 says EMD should ordinarily not exceed 1% of procurement value. It identifies approved payment forms and allows categories expressly exempted by the government.
For example, a ₹2 crore procurement would ordinarily imply no more than ₹2 lakh. The rule recognises electronic payment, demand drafts, bankers’ cheques, specified savings instruments and approved irrevocable bank guarantees. Government-notified exemptions still apply. This is a ceiling, not a direction to charge exactly 1% on every tender.
3. Kerala: check the purchasing authority
The Kerala Stores Purchase Rules ordinarily require 1% of total cost for tenders worth ₹20,000 or more. That means ₹50,000 on a ₹50 lakh store purchase. The official text lists exemptions for certain established or registered firms and khadi and village industries, and says the earlier SSI exemption was withdrawn.
These provisions concern stores purchasing; they must not be presented as a universal Kerala public-works rate.
4. Maharashtra: departmental conditions matter
Maharashtra procurement covers state departments, municipal bodies and separate public undertakings.
A universal 1% or 2% claim would therefore be misleading. The legally meaningful figure is the rate fixed under the issuing authority’s applicable procurement instructions and stated in its bid schedule. The absence of one verified statewide figure is not itself an exemption.
5. Uttar Pradesh: read the NIT and works conditions
Uttar Pradesh public works, supplies and corporation tenders do not all arise under the same standard contract. Check the applicable departmental rules and current tender conditions before determining the EMD amount.
A bidder should therefore distinguish a PWD works contract from a supply contract or a utility procurement. The amount shown in the governing tender conditions is the applicable figure, rather than an assumed GFR goods percentage.
6. Rajasthan: EMD Rajasthan RTPP
Rule 42 of the Rajasthan Transparency in Public Procurement Rules, 2013 generally specifies 2% of the estimated procurement value for covered competitive methods, unless the state prescribes otherwise.
For qualifying Rajasthan MSMEs, the rule provides a 0.5% concession on the relevant offered quantity or service. It also excludes bid security for petty purchases up to ₹10,000 and certain specified procurement methods.
It also recognises bank guarantees, e-bank guarantees and insurance surety bonds, among other forms. The bid-security instrument must remain valid 30 days beyond bid validity. These details make Rajasthan different from GFR’s ordinary 45-day buffer. Because the rule has been amended, use the current consolidated text, not an older tender template.
7. Telangana: tender category comes first
Telangana works, supplies and corporation tenders may use different departmental instructions. Identify the buyer and tender category before treating a percentage as standard. Review the EMD schedule, electronic payment process, eligible exemptions, and bid validity. A tender issued by a state utility may not mirror a roads department tender.
Want to reduce cash tied up across simultaneous bids? axiTrust explains replacing cash EMD with bid bonds and the surety bond eligibility checks that insurers may apply. An insurance bond is an option only when the buyer accepts it.
Railway, CPWD and PSU EMD requirements
These buyers need a separate check because their manuals and standard tender documents can differ from general state rules. A contractor who regularly bids across departments should maintain a separate checklist for each buyer.
1. Indian Railways: EMD railway works versus stores
For EMD railway works, the Railway Board’s current standard conditions and the relevant IREPS tender are the first documents to inspect.
Older railway engineering guidance describes a slab calculation for works: 2% up to ₹1 crore, followed by ₹2 lakh plus 0.5% on the excess. That historical formula should not be presented as universally current without checking the latest Railway Board instructions.
Railway stores procurement can have separate rules and exemptions. In short, EMD railway amounts should be taken from the live tender, not a generic calculator.
For the separate issue of bond acceptance, axiTrust discusses Indian Railways and insurance surety bonds. That discussion should not be mistaken for a statutory EMD rate.
Fun fact: Railways buys everything from track works to small replacement parts. One buyer name can therefore cover very different procurement procedures. |
2. CPWD: distinguish EMD from performance guarantee
CPWD construction contracts distinguish EMD at bidding from performance guarantees and security deposits after award. Those later securities protect contract delivery, not the initial offer.
GFR’s goods-procurement percentage should not be copied into a construction bid. axiTrust’s article on CPWD insurance surety bonds explains the related bond route, subject to tender acceptance.
3. PSUs: buyer-specific procurement policies
PSUs may buy goods, services or construction work under different manuals. Eligible MSE benefits can apply to covered central public-sector purchases, but they should not be assumed for every works tender or every enterprise holding Udyam registration.
Can insurance surety bonds be a better alternative to cash EMD?
Cash EMD ties up working capital, while bank guarantees may use your available banking limits. Insurance surety bonds offer another route, allowing eligible contractors to secure bids without necessarily blocking equivalent cash or bank limits.
This can be particularly useful when bidding for multiple projects simultaneously. However, acceptance depends on the tender, and insurers may require collateral or additional checks.
axiTrust helps contractors explore suitable surety bond options, understand eligibility requirements, and navigate the application process through its technology platform, making it easier to assess alternatives before committing funds.
FAQs
Are EMD rules the same for every state?
No. State procurement laws, departmental manuals, and individual tender conditions differ. The tender notice is the practical starting point.
Does Udyam registration always remove EMD?
No. Eligibility depends on enterprise category, activity, procurement type, and the buyer’s applicable policy. Read the exemption clause.
Can insurance surety bonds replace cash EMD?
GFR Rule 170 permits them for central goods procurement. Other buyers must accept the instrument in their tender conditions.